Repository source: docs/plans/calendar_ics_feed/calendar_ics_feed_step4_implementation_summary.md
Calendar iCal feed Step 4 implementation summary
Debug mode: enabled
Effort study: railspike-effort / v3/calendar_ics_feed; host ledger. Standing P2 enrollment; extended estimates enabled.
Cycle estimate: 0.55
Branch feat/calendar-ics-feed, replayed onto f05cc94 when push access arrived; planning commit ab5c89f, Stage 1 fc4c007. PR #324 (Steps 1–3, Stages 1–2) was merged 2026-11-17. Later stages continue on feat/calendar-ics-routes from 3e1b719, per AGENTS.md follow-up rules. Stage 3 went out in #325, merged 2026-11-17. Stage 4 is on feat/calendar-ics-event-links from 08a8cce.
Step 4 entry
Step 3 approved 2026-11-17. Whole-cycle projection 0.55 reaffirmed after the planning commit. Stage originals 0.05/0.12/0.12/0.10/0.10/0.05/0.03 copied from Step 3, non-additive. Claude single exposed rater; R1 hashes not re-verified.
Stage 1 - Google probe
Original estimate: 0.05
Status: partly checked. Stage 2 started before the remaining checks, at the maintainer's request (2026-11-17), with floating times as planned; a shifted time would revise Stage 2's time format.
Changes:
New
docs/plans/calendar_ics_feed/google_probe.ics. Probe A is a tentative event on 2026-11-20 at 19:00 with no time zone. Probe B is a confirmed all-day event from 2026-11-27 to 2026-11-29, with a place and a URL.
Verification:
Parsed with the Python
icalendarpackage: both events read back with the intended start, end and status. Passed.No line exceeds 75 octets; lines end in CRLF. Passed.
Google checks on Ilya's iPhone: pending. The branch cannot be pushed from this session, so the probe has no raw GitHub URL. Revised route: Ilya copies the file to
public/on the zenmemes.com server, so it is served athttps://zenmemes.com/google_probe.ics, and removes it afterwards.
Checks for Ilya, with results to record here:
Subscribe link on the iPhone: passed (maintainer, 2026-11-17). The link opened Google Calendar and offered to add the calendar. Google shows that offer before it fetches the file, so this does not yet show that the events arrived. At 23:40 UTC
https://zenmemes.com/google_probe.icsreturned 404."From URL" on calendar.google.com: does the calendar appear?
Probe A: shown at 7:00 PM on Fri Nov 20, or shifted?
Probe B: three days, Nov 27 to Nov 29, or four?
Event-template link: does Google's event form open filled in, at 7:00 PM?
Notes:
Deviation from Step 3: the probe is served from zenmemes.com instead of a raw GitHub URL, because this session cannot push. Same purpose and scope.
Stage 2 - iCal writer and flag
Original estimate: 0.12
Retrospective: 0.10
Changes:
New
src/ForumRewrite/Calendar/CalendarIcs.php.document()takes event rows shaped likeCalendarQuery::eventsBetween, a thread-to-state map fromEventStatus, the site URL and a calendar name.All-day events use DATE values with an end the day after the last day. A timed event starts at
Event-Timewith no zone and ends an hour after that time on its last day.UID is
<thread_id>@<host>. STATUS is CONFIRMED for a confirmed event and TENTATIVE otherwise. The DESCRIPTION holds the phrase, the link and the thread URL. Text is escaped, lines are folded at 75 octets on character boundaries, and lines end in CRLF.New flag
FORUM_CALENDAR_FEED_ENABLED("Calendar feed"): site-mutable, on, requires Event support, in the AUTHORING group after Event phrases.
Verification:
./v3 test --smoke CalendarIcsTest FeatureFlagEvaluatorTest: 478 passed. Full suite not run.Correction (2026-11-18):
CalendarIcsTestwas not registered intests/run.php, so it did not run in Stage 2; the 478 count did not include it. Stage 4 registered it, and all its cases pass. NewCalendarIcsTest: one-day, multi-day, timed, timed multi-day across midnight, tentative and confirmed, escaping, the description, folding of Cyrillic text, and skipping rows with a bad date.FeatureFlagEvaluatorTest: both registry lists updated for the new flag.A two-event sample with a long Cyrillic title read back through the Python
icalendarpackage with the intended dates, times, status, title and description.
Notes:
Step 3 named no end for timed events. Decision: a one-hour length, because
Event-Timehas no end time and a calendar entry with no end shows as a zero-length tick. New understanding, not changed scope.Nothing reads the flag yet; Stage 3 adds the routes.
Estimate details: as planned; the writer was simpler than estimated.
Stage 3 - Feed routes
Original estimate: 0.12
Retrospective: 0.10
Trigger: after deploying #324, the maintainer got a 404 at
/calendar.ics. That was expected, because #324 had no routes; this stage adds them.Changes:
CalendarQuery::eventsBetweenalso selectsevent_linkandevent_when.New
CalendarPageController::feed(?string $tag). It reads events from 90 days ago to two years ahead with the grid's query and states, drops declined events, and writes them withCalendarIcs. The site origin comes fromTemplateRenderer::requestOrigin(). The calendar name is the site's display name, plus#tagfor a tag feed. Returns null while event support or the feed flag is off.Application:/calendar.icsand/calendar/<tag>.ics, checked before the calendar page routes. They sendtext/calendar; charset=utf-8with a five-minute public cache, or 404. Both are added toisApplicationRoute.membersOnlyRequestAllowedis unchanged, so members-only sites keep the feed behind sign-in.
Verification:
./v3 test --smoke CalendarPageTest CalendarIcsTest: 490 passed. Full suite not run.New
CalendarPageTestcases: the feed lists the grid's events with dates relative to today, leaving out declined, anonymous and too-old events; confirmed and tentative status; the tag feed lists only its tag; 404 with event support off and with the feed flag off, while the tag page still works; and on a members-only site, signed-out visitors don't get the feed.Local server with event support on:
/calendar.icsreturned 200,text/calendar; charset=utf-8,Cache-Control: public, max-age=300./calendar/general.icsreturned 200 and/calendar.ics/returned 404.zenmemes.com after deploy:
/calendar.icsreturned 200text/calendarwith 30 events. The maintainer subscribed on his iPhone and Google Calendar showed a ZenMemes all-day event over the right dates (screenshot, 2026-11-17).Found in production: every event's title came through as "Event", because most event threads have no subject. Fixed in Stage 4. Google also showed the thread link as
http://, because the subscribe link usedwebcal://, which Google fetches over HTTP; Stage 5's link will use the HTTPS address.
Notes:
The Stage 1 time checks are still open. The live feed can now stand in for the probe file.
Estimate details: as planned.
Stage 4 - Per-event file and Google link
Original estimate: 0.10
Retrospective: 0.12
Changes:
Production fix:
CalendarIcs::title()names an event with the thread's display title, the one the grid shows (ThreadTitle::displayTitleover subject and text), so threads with no subject no longer arrive as "Event".CalendarQuery::eventForThread()returns one listed, unretracted thread's event, sharing the select witheventsBetween. Like the event block, it doesn't require an approved author.CalendarPageController::eventFile(), and the/threads/<id>.icsroute ahead of the thread route. It sendstext/calendaras a download, or falls through to the normal 404.CalendarIcs::googleEventUrl()builds Google's filled event form, with dates that have no time zone, like the feed.New
templates/partials/event_calendar_links.php, shown after the event block inthread_root_card.php. That partial only appears on thread pages, so board rows and cards are unchanged. It reads "Add to Google Calendar · .ics" and appears only while event support and the feed flag are on, and never for a retracted post. The renderer exposescalendarFeedEnabled.tests/run.phpregistersCalendarIcsTest.
Verification:
./v3 test --smoke CalendarPageTest CalendarIcsTest: smoke 492 passed, andCalendarIcsTeston its own 10 passed. It was not in the smoke run because it was registered after that run. Full suite not run.New cases: a title taken from the text when there is no subject; the Google link for all-day and timed events; the thread page shows the links, while a plain thread and the board don't; the
.icsfile of an anonymous author's event has one event with its title; a thread with no event and an unknown thread both return 404; with the feed off, the event block stays but the links and file are gone.
Notes:
The Google link leaves out the thread address. Thread pages are cached HTML that must be the same for every visitor, and the origin isn't known when the page is built. The
.icsfile includes the address, because it is built per request.
Estimate details: a bit over, because of the production title fix and the missing test registration.
Stage 5 - Subscribe panel
Original estimate: 0.10
Retrospective: 0.08
Approval: on 2026-11-18 the maintainer asked us to finish the remaining stages without waiting for his approval.
Changes:
templates/pages/calendar.php: a closed<details>Subscribe panel under the month links, shown while the feed flag is on. It holds Add to Google Calendar, "Other calendar apps" (webcal:), the.icslink, the feed address in a read-only field, and one line about Google's refresh delay. A tag calendar offers its own tag feed.A script fills the absolute feed address from
location.originbefore paint. Cached pages stay identical for every visitor, and a page on HTTPS gives Google an HTTPS address, which avoids thewebcal:plain-HTTP fetch seen in Stage 3. Without script, the.icslink and the relative address remain, and the Google and app links stay hidden.public/assets/calendar.css: panel spacing, and a 16px address field so iPhone Safari doesn't zoom.
Verification:
./v3 test CalendarPageTest: 15 passed. New case: the panel on/calendarand/calendar/couchesnames each page's own feed, and is absent with the feed flag or event support off.node tests/browser/calendar.mjs: passed. New checks: at 390px and 1280px the panel starts closed, opens with the page-origin address and with Google andwebcal:links, and still fits the width; the feed fetches as an iCal document. Without JavaScript, the.icslink and the relative address remain and the Google link is hidden. The existing theme sweep (Light, Dark, Chicago, Midnight, Word97 at both widths) still fits.Looked at the 390px screenshot with the panel open: it sits under the month links and fits the card.
Notes:
Deviation from Step 3: no copy button, so no copy code moved out of the Prompts page. Stage 1 showed the Google link works on the iPhone, which makes the address a fallback, and a read-only field can be selected and copied by hand. That follows the AGENTS.md guidance to keep UI minimal and avoids touching the Prompts page. A copy button can follow if the field proves awkward.
Google is given an
https:feed address in its subscribe link. Stage 1 only tested thewebcal:form, so this is checked in Stage 7.
Estimate details: smaller than planned, without the copy-code move.
Stage 6 - Documentation and concepts
Original estimate: 0.05
Retrospective: 0.05
Changes:
docs/reference/calendar.md: new "Subscribing" section covering the feeds, the window and states, event identity and naming, timing, the Subscribe panel, per-event links and file, members-only behaviour, and the flag.docs/concepts/calendar.md: "export" removed from the Boundary, which now points to the new concept.New
docs/concepts/calendar_feed.md(purpose, scenario, sources, boundary).docs/reference/agent_api.md: the three iCal reads, in the Events section.docs/plans/README.md: entry updated to the delivered state.
Verification:
Every relative link in the new concept file resolves;
git diff --checkis clean.Concept entries checked against delivered behaviour: no full-inventory audit.
Notes: documentation only; runtime checks not applicable.
Stage 7 - Production check on the maintainer's iPhone
Original estimate: 0.03
Status: pending maintainer. This needs Stages 4–5 deployed, after this PR is merged.
Already shown (Stage 3, 2026-11-17): Google Calendar on the iPhone subscribed to
/calendar.icsand showed a ZenMemes all-day event over the right dates.Still to check after deploy:
Event titles appear in Google (not "Event") after Google's next refresh.
A timed event shows at the time written. This is the open Stage 1 time-zone risk; no ZenMemes event with a time was seen yet.
Subscribe → Add to Google Calendar on
/calendarworks on the phone with thehttps:address."Add to Google Calendar" on an event thread opens a filled form.
No retrospective until the check is done.
Final verification
Planned stages: Stages 1–6 complete and committed; Stage 7 pending the maintainer's phone check after deploy.
Stage commits: planning
ab5c89f; Stage 1fc4c007; Stage 2377d149; Stage 3de1d6d9; Stage 4349afb5; Stage 5c58b592; Stage 66bb5e0d. Seven commits across three PRs (#324, #325, #326) for six completed stages: passed (needs at least 1 + 6).Planning commit holds only approved plans, the debug log and the index entry: passed.
Completion Contract:
Normal entry, the Subscribe panel and event-thread links: passed locally (browser test).
End-to-end subscription: partly passed on production (Stage 3 screenshot); the rest is pending Stage 7.
Recovery, the copyable address and the refresh note: passed locally.
Deployment, no schema or dependency change: passed.
Tests:
./v3 test --smoke CalendarPageTest CalendarIcsTest FeatureFlagEvaluatorTest, 503 passed;node tests/browser/calendar.mjspassed. Full suite not run, per AGENTS.md. No baseline failures found.Dependencies: none added.
playwright-core@1.58.1, already declared inpackage.json, was installed outside the repository (--no-save) to run the browser test.Final diff review over
src,templates,publicandtestsfor this branch: no stray changes./threads/<id>.icsfalls through to the normal thread route, giving a 404 when there is no event.Shared consumers:
thread_root_card.phpis used only bythread.php;event_block.phpis unchanged; the calendar page script is shared by the grid only.Themes: the browser test's theme sweep (Light, Dark, Chicago, Midnight, Word97) fits at 390px and 1280px. No navigation destination was added, so no nav icons were needed.
Feedback items: none.
Cycle retrospective
Cycle estimate: 0.55
Retrospective: 0.55
The production fixes (event titles, test registration) and the three-PR split added work. Dropping the copy button saved some.
Maintainer comfortable-fit judgment: pending.
— Claude · 2026-11-17 UTC · Model: Claude Opus 5.5